Project Summary |
|
Alpine Summit |
Printable Document (.pdf) |
|
The AB Stones has defeated its competitors once again with its incredible 12-degree
setback. This project in Walker, Michigan needed two large retaining walls to support a parking lot. The
Allan Block product got the job done because it is the only segmental block produced with a 12-degree
batter.
|
|
![]() |
PROJECT NAME & LOCATION Alpine Summit -Walker, MI PRODUCT AB Stones PROJECT SIZE 11,006 ft2 (1,023 m2) LOCAL ENGINEER Holland Engineering GENERAL CONTRACTOR/WALL BUILDER GDK Properties & Kent Companies ALLAN BLOCK MANUFACTURER Atlas Block, Ontario, Canada |
PlanAlpine Summit, in Walker, Michigan was in need of some large retaining walls to support a large parking lot on their site. During the biding process they narrowed their choices to two blocks, Rockwood's Classic 6 degree block and Allan Block's 12 degree Stones. This story would end right here had they chosen Rockwood, but fortunately for them and for us they chose the AB Stones. |
![]() |
|
The 12-degree block was the best
choice for this project for several reasons. The
Stones not only decreased the amount of geogrid
reinforcement needed for the project but also cut
the excavation costs considerably. Atlas Block was
contacted by Kent Companies to design the retaining
walls. The site plans and soils reports were sent to
the Allan Block corporate office for a preliminary
design to be made. Then passed on the local
engineer, Holland Engineering, who was responsible
for the final design. |
|
DesignThe plans called for over 800 linear feet (244 m) of retaining wall and 11,000 blocks to stand in two locations on the site. The maximum wall heights were set at 16 ft (4.9 m) with only one type of geogrid, Miragrid 3XT, to be used at maximum lengths of 8 ft (2.4 m). The soil conditions were considered "average" and called for a 29-degree friction angle for the design. Which is typical for clay/sand-type soil conditions. Once the designs were finished, the real work of building could begin. |
|
|
|
BuildThis was Kent Companies' first experience using the Allan Block product. They had previously focused their attention on building hundreds of smaller-sized retaining walls, however they had not built a wall of this magnitude nor had they utilized Allan Block's unique block design. To help train their installers on the process from start to finish, Atlas Block created a PowerPoint presentation that walked them through the entire installation process. The building timeline was extremely tight because the wall was needed immediately. Instead of starting construction at the lowest point in the wall, construction had to begin on the high side, due to the fact that some portions of the site were not yet excavated. This was especially difficult because of the downward slope of the wall as well as the estimating involved in the correct starting height. |
|
|
For a first-time Allan Block installer, this presented quite
a challenge. However, with proper guidance from the Atlas
Block and Allan Block Corporate team, all these obstacles
were resolved with impressive results. In addition to the
step-downs, a storm sewer pipe and manhole were also a major
concern in the installation process. The contractor had
already installed the storm sewer pipe and manhole that were
to be located directly behind the wall. Having such a layout
works well with the wall design, however it is the
recommendation of Allan Block to always install storm sewer
pipe as the retaining wall is being installed to ensure
proper placement of geogrid around the two structures.
|
![]() |
|
Since the pipes had already been installed, the
contractor decided that it was not practical to move
the storm sewer pipe to put the geogrid in the wall.
Allan Block and Holland Engineering suggested that
the contractor dig out behind the storm pipe, place
the geogrid behind the pipe, and then fill in the
portion between the pipe and the wall with 0 percent
fines concrete. This would ensure that any leaking
water would not affect or damage the retaining wall.
Below is a diagram of the actual section.
|
|
![]() |
![]() |
Once all of these obstacles were hurdled, the wall construction went very smoothly. The walls were finished in no time and the Alpine Summit has beautiful 12-degree walls to hold up their parking lot. Another job well done! |
|








