Designing Your Fence Layout
Step 1: Laying Out & Drilling the Piles
|
-
Review the approved construction design for post spacing and horizontal alignment.
-
Have corners on your project? See the layout procedures for
fence corner installation
or download AB Fence Tech Sheet #2005.
-
Mark out the center of each pile per the requirements of the approved
construction design. Suggested methods of doing this include:
string line to establish the overall layout of your fence, a steel chain
to develop precise duplicated spacing between posts, or by having the
points set by a surveyor.
-
Establish offsets to the center of the piles for later reference by using
a substantial grade stake that is not easily displaced.
-
Excavate a 6 in. (150 mm) deep by 12
in. (300 mm) wide trench the entire
length of the fence. The centerline of
the trench should also be the centerline
of the AB Fence placement.
Trench Dimensions
|
-
Relocate post center locations using construction offsets and a string line.
-
Excavate the pile holes to the depth and diameter specified in the approved construction design.
-
When drilling the holes keep in mind that hole positioning is critical.
A maximum allowable deviation of ±1 in. (25 mm) for the pile cap is
allowed for the horizontal locations.
See Figure 8.
-
When the pile holes are excavated each hole must be checked to
make sure loose material is not at the bottom of the hole. Use a long
handled hand tamper to compact this soil when necessary.
-
Soils engineers will need to verify the bearing capacity at the bottom of the pile.
-
Check with your local building officials to see if a site visit is required for pile inspection.
Note: The soil that the AB Fence is built on must be compacted and
capable of supporting the weight of the structure.
|
Step 1: Mark the Center of Each Pile
Step 1: Establish Offsets to the Center of the Piles
Step 1: Dig the Trench
Step 1: Auger Pile Holes
| Typical Pile Footing Excavation |
Cohesive Soils
Standard concrete form 12 in. (305 mm) depth.
|
|
Granular Soils
Extended concrete form depth.
|
|
Step 2: Forming the Piles
-
Use a concrete form, or alternate cylindrical tubing material, to form
the top of the pile hole to create a pile cap. The form should have
the same inside diameter as the design pile diameter, and be a minimum
of 12 in. (300 mm) deep. Additional length may be required if
the sides of the excavation cave in, which is typical for granular soils.
-
Place the concrete form in the hole, making sure that the center
of the concrete form is in alignment with the centerline of the AB Fence to ±1 in. (25 mm), see Figure 8.
-
Using a laser level, transit or string level, set the top of the concrete
form level with or no more than 1 in. (25 mm) below the design elevation
of the top of the pile. Use hand levels to level each concrete
form pile cap individually.
-
The concrete form can either be braced against the sides of the hole or staked to maintain elevation
and location during casting. For a cross section of the pile hole see Figure 9.
|
Step 2: Place the Concrete Form
Level Piles
|
Step 3: Pile Spacing
-
To set the exact spacing between each AB Fence post, use the
AB Fence Pile Layout Jig
-
Mark the placement of the rebar in the pile, using the
Post Block Template
during the pile pour. For more information see the
construction detail.
-
Spacing between each pile must be maintained to a tolerance of ± 0.5 in.(13 mm) to allow for proper interlock between post and panel sections.
|
|
|