Allowable Construction Tolerances |
Download: .PDF .DOC |
Construction Tolerances |
|
|
To ensure that acceptable work standards are understood during
retaining wall installation, construction tolerances need to be
established. These construction tolerances should consider that
the retaining wall is designed to be a flexible structure that tolerates
horizontal and vertical variation. However, too much variation
can affect the structural stability of the wall. To maintain horizontal and vertical control, adjustments may be required during modular block installation. Even with tight quality control procedures by block manufactures, modular block units may vary in height. Shimming a maximum of 0.125 in. (3 mm) per block is acceptable construction practice. It is recommended that shimming material be asphaltic or non-degradable products. Acceptable construction tolerances are illustrated in Figures 13 thru 16. |
![]() Figure 13: Vertical Control |
Differential Settlement |
|
|
Foundation settlements must be estimated with great care for buildings,
bridges, towers, power plants, and similar high-cost structures.
For structures such as fills, earth dams, levees, and retaining walls a
greater margin of error in settlements can usually be tolerated. The
construction method of placing the dry-stacked mortarless Allan
Block on an aggregate leveling pad creates a flexible but stable
retaining wall. Settlement errors that are acceptable while maintaining
structural integrity include large total wall settlement and
moderate differential settlement as depicted in Figure 14. Settlement occurs when the weight of the retaining wall structure exceeds the bearing capacity of the soil. Cohesionless soils consisting of sands and gravels often exhibit very little settlement with most of the settlement occurring during or shortly after wall construction. Cohesive soils with high moisture content have the potential for large time-depended settlement because the weight of the wall can actually compress the foundation soil. The settlement can be estimated using conventional one-dimensional consolidation calculations. When anticipated settlement is greater than the construction tolerances, special design and construction steps need to be taken. |
|
![]() Figure 14: Differential Settlement |
|
|
Post Construction Finish and Appearance |
|
|
Depending on wall heights, surcharges, soil conditions and foundation
materials, some stress cracks may occur in the wall during and
after construction. Since Allan Block walls are flexible structures,
some cracking of block is likely, as are spaces between blocks as the
wall moves. These openings should not exceed 0.25 in. (6 mm) and
do not affect the structural integrity of the wall. |
|
![]() Figure 15: Horizontal Control |
![]() Figure 16: Rotation |